With the local utility one-time charges, and requirements to trench approximately 100′ × 30″ deep, getting 3-phase ‘from the grid’ was expensive. I’d then start being charged commercial/industrial rates for the power used.

The Phase Perfect was $5,500; 3-phase panel and installation another $500: so, I’m $6k invested at this point.

It is about this time I start questioning my sanity…

MJCD